Background History

2000-2001

Charlotte/Martha Sabordinate Service District

(CMSSD)

horizontal rule

Exhibit 2 - Proposed CMSSD Sanitary Sewer Collection System 

Timeline of key milestones from

McCombs Frank Roos Associates:

September 12, 2000    Draft Report submitted to Wright County
October 3, 2000    Informal area meeting held with residents
October 10, 2000    Final Report presented to Wright County
October 30, 2000    Formal public hearing held
November 14, 2000    Approval of resolution creating CMSSD
November 27, 2000    Publication of CMSSD resolution
January 1, 2001    Effective date of CMSSD creation

February 6, 2001   

Referendum deadline (no opposition)
February 13, 2001    Wright County Board orders preparation of plans and bids
April 18, 2001    Bids are received
May 1, 2001    Improvement Bonds are sold
May 1, 2001    Apportionments are levied
May 8, 2001   

Contract Awarded

November 19, 2001    Construction completed

horizontal rule

Handouts from 2020

Advisory Committee Meetings

Pages 1 2 3 4 5 6

CMSSD Rules

Copy of Lake Charlotte Martha Bond and Specials Balance

________________________________

[Top of Page]